File #: 24-0291   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 4/1/2024
Title: Fire Station 223 - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 1) A pre-construction services contract is needed to develop the project design,review the design for constructability, prepare cost estimates, and develop the project schedule and project phasing plan. Staff recommend selecting Willmeng Construction Inc. as the CMAR for this project and awarding a pre-construction services contract in the amount of $100,825. This project is funded by 2022 Public Safety Bonds.
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Fire Station 223 - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 1)

 

A pre-construction services contract is needed to develop the project design,review the design for constructability, prepare cost estimates, and develop the project schedule and project phasing plan.

 

Staff recommend selecting Willmeng Construction Inc. as the CMAR for this project and awarding a pre-construction services contract in the amount of $100,825. This project is funded by 2022 Public Safety Bonds.