File #: 23-0975   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 9/11/2023
Title: Signal Butte Water Treatment Plant Expansion - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 (District 6) This is the first of two GMP projects. GMP No. 1 includes the construction of a second 8-million-gallon storage reservoir as well as plant redundancies which are vital to ensuring that the plant operates efficiently and reliably until full build-out. Staff recommends awarding a construction services contract to the CMAR, McCarthy Building Companies Inc., in the amount of $56,603,484.00 (GMP), and authorizing a change order allowance in the amount of $2,830,174.20 (5%), for a total amount of $59,433,658.20. This project is funded by Utility Systems Revenue Obligations.
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Signal Butte Water Treatment Plant Expansion - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 (District 6)

 

This is the first of two GMP projects. GMP No. 1 includes the construction of a second 8-million-gallon storage reservoir as well as plant redundancies which are vital to ensuring that the plant operates efficiently and reliably until full build-out.

 

Staff recommends awarding a construction services contract to the CMAR, McCarthy Building Companies Inc., in the amount of $56,603,484.00 (GMP), and authorizing a change order allowance in the amount of $2,830,174.20 (5%), for a total amount of $59,433,658.20. This project is funded by Utility Systems Revenue Obligations.