Title:
|
Approving and authorizing the City Manager to enter into three separate Intergovernmental Agreements (IGAs) with the Flood Control District of Maricopa County for the design, right-of-way acquisition, utility relocation, construction, construction management, and operation and maintenance of drainage improvements within the City. (Districts 3 and 4) - Resolution No. 12031
The three proposed IGAs are for the following projects: 1) 2nd Avenue and Spencer Project - south of Main Street and west of Stapley Drive (District 4); 2) Guthrie Street and Main Street Project - north of Main Street and west of Gilbert Road (District 4); and 3) Main Street and Phyllis Street Project - north of Main Street and west of Dobson Road (District 3).
The Flood Control District of Maricopa County will fund 75% of the project design and construction costs incurred for each project up to a maximum contribution of $750,000 per project. The City's contribution for all three projects is estimated to be $625,9...
|