Title:
|
Water Transfer Station No. 02 Upgrades - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 5)
This GMP No. 2 includes the purchase and temporary storage of equipment and materials that have long-lead times, including pumps, electrical equipment, and valves.
Staff recommends awarding a construction services contract to the CMAR, J.R. Filanc Construction, in the amount of $1,335,375.97 (GMP No. 2), and authorizing a change order allowance in the amount of $66,768.80 (5%), for a total amount of $1,402,144.77. This project is funded by Water Utility Systems Revenue Obligations.
|