Title: Water Transfer Station No. 02 Upgrades Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 (District 5) This is the first of first of three GMPs for this project. GMP No.1 includes the inspection of the existing waterline and the installation of a dewatering standpipe at the intersection of Recker and Brown Roads. Staff recommends awarding a construction services contract to the CMAR, J.R. Filanc Construction, Inc., in the amount of $766,829.96 (GMP), and authorizing a change order allowance of the amount in $38,341.47 (5%), for a total amount of $805,170.81. This project is funded by Utility Systems Revenue Obligations.
Attachments: 1. Council Report, 2. Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Water Transfer Station No. 02 Upgrades Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 (District 5)

 

This is the first of first of three GMPs for this project. GMP No.1 includes the inspection of the existing waterline and the installation of a dewatering standpipe at the intersection of Recker and Brown Roads.

 

Staff recommends awarding a construction services contract to the CMAR, J.R. Filanc Construction, Inc., in the amount of $766,829.96 (GMP), and authorizing a change order allowance of the amount in $38,341.47 (5%), for a total amount of $805,170.81. This project is funded by Utility Systems Revenue Obligations.