File #: 22-0721   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 6/6/2022
Title: Northwest Water Reclamation Plant Process Improvements - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 3) The Northwest Water Reclamation Plant (NWWRP) was originally constructed in 1988 and expanded in 2000. A recent facility study performed an in-depth evaluation of all the treatment processes for the current capabilities and future needs and developed recommendations to upgrade the facility. Staff recommends selecting Archer Western Construction, as the CMAR for this project, and awarding a pre-construction services contract in the amount of $950,769. This project is funded by Utility Systems Revenue Obligations.
Attachments: 1. Council Report, 2. Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Northwest Water Reclamation Plant Process Improvements - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 3)

 

The Northwest Water Reclamation Plant (NWWRP) was originally constructed in 1988 and expanded in 2000.  A recent facility study performed an in-depth evaluation of all the treatment processes for the current capabilities and future needs and developed recommendations to upgrade the facility.

 

Staff recommends selecting Archer Western Construction, as the CMAR for this project, and awarding a pre-construction services contract in the amount of $950,769.  This project is funded by Utility Systems Revenue Obligations.