File #: 20-0828   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 8/31/2020
Title: Lewis East Substation Rebuild Project - Construction Manager at Risk (CMAR) and Pre-Construction Services Contract (District 4) This project will replace the 45-year-old transformer and associated switchgear and up-size the existing 22.4 megavolt-amperes (MVA) transformer to a 28 MVA transformer to support downtown’s growing electrical demand. In addition to the equipment replacement, portions of the substation facility will be re-arranged to provide greater flexibility for routine maintenance. The rearrangement will necessitate site grading, new concrete pads to accommodate the larger substation transformer footprint, and other ancillary support structures. Staff recommends selecting Builders Guild Inc.(a Mesa business) as the CMAR for this project and awarding a Pre-Construction Services contract in the amount of $75,189. This project is funded by 2014 Electric bonds.
Attachments: 1. Council Report, 2. Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Lewis East Substation Rebuild Project - Construction Manager at Risk (CMAR) and Pre-Construction Services Contract (District 4)

 

This project will replace the 45-year-old transformer and associated switchgear and up-size the existing 22.4 megavolt-amperes (MVA) transformer to a 28 MVA transformer to support downtown’s growing electrical demand.  In addition to the equipment replacement, portions of the substation facility will be re-arranged to provide greater flexibility for routine maintenance. The rearrangement will necessitate site grading, new concrete pads to accommodate the larger substation transformer footprint, and other ancillary support structures.

 

Staff recommends selecting Builders Guild Inc.(a Mesa business) as the CMAR for this project and awarding a Pre-Construction Services contract in the amount of $75,189.  This project is funded by 2014 Electric bonds.