Title: Central Mesa Reuse Pipeline - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 4 (Districts 1, 3, and 6) GMP No. 4 includes the early procurement of electrical gear, pumps, motors, and associated materials for the plant improvements that will utilize delivery of reclaimed water produced at the Northwest Water Reclamation Plant as part of a water exchange agreement with the Gila River Indian Community. Staff recommends awarding a construction services contract to the selected CMAR, Garney Companies, in the amount of $10,096,000.00 (GMP No. 4) and authorizing a change order allowance in the amount of $504,800.00 (5%), for a total amount of $10,600,800.00. This project is funded by the Water Utility Systems Revenue Obligations
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Central Mesa Reuse Pipeline - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 4 (Districts 1, 3, and 6)

 

GMP No. 4 includes the early procurement of electrical gear, pumps, motors, and associated materials for the plant improvements that will utilize delivery of reclaimed water produced at the Northwest Water Reclamation Plant as part of a water exchange agreement with the Gila River Indian Community.

 

Staff recommends awarding a construction services contract to the selected CMAR, Garney Companies, in the amount of $10,096,000.00 (GMP No. 4) and authorizing a change order allowance in the amount of $504,800.00 (5%), for a total amount of $10,600,800.00. This project is funded by the Water Utility Systems Revenue Obligations