File #: 18-1343   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 12/3/2018
Title: Horne Road Improvements Project (6th Avenue to Southern Avenue) Construction Manager at Risk, Guaranteed Maximum Price (GMP) No.2 (District 4) This portion of the project includes the scope of work necessary to complete the proposed pavement improvements; water and gas replacements; electric undergrounding; and new storm drain and sewer chemical feed line. Staff recommends awarding the contract for GMP No. 2 to Haydon Building Corporation in the amount of $6,340,879.73, and authorize a change order allowance in the amount of $317,043.99 (5%), for a total award of $6,657,923.72. This project is funded by Local Street Sales Tax, 2010 and 2014 authorized Electric Bonds, and 2014 authorized Water, Wastewater and Gas bonds.
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Horne Road Improvements Project (6th Avenue to Southern Avenue) Construction Manager at Risk, Guaranteed Maximum Price (GMP) No.2 (District 4)

 

This portion of the project includes the scope of work necessary to complete the proposed pavement improvements; water and gas replacements; electric undergrounding; and new storm drain and sewer chemical feed line.

 

Staff recommends awarding the contract for GMP No. 2 to Haydon Building Corporation in the amount of $6,340,879.73, and authorize a change order allowance in the amount of $317,043.99 (5%), for a total award of $6,657,923.72.  This project is funded by Local Street Sales Tax, 2010 and 2014 authorized Electric Bonds, and 2014 authorized Water, Wastewater and Gas bonds.