Ellsworth Road South City Limits to Ray Road, Construction Manager At Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 1 (District 6)
Project improvements include widening Ellsworth Road by adding a third lane in each direction, milling and overlaying the existing pavement, installation of medians, curb and gutter, sidewalk, and streetlights. Benefits will include reduced congestion, safer pedestrian crossings, bicycle lanes, and increased accessibility to local businesses.
Staff recommend awarding a contract to Sundt Construction in the amount of $27,177,832.52 (GMP), and authorizing a change order allowance in the amount of $2,717.783 (10%), for a total authorized amount of $29,895,615.52. This project is funded by 2020 Street bonds and the Transportation Fund.
|
Title
Ellsworth Road South City Limits to Ray Road, Construction Manager At Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 1 (District 6)
Project improvements include widening Ellsworth Road by adding a third lane in each direction, milling and overlaying the existing pavement, installation of medians, curb and gutter, sidewalk, and streetlights. Benefits will include reduced congestion, safer pedestrian crossings, bicycle lanes, and increased accessibility to local businesses.
Staff recommend awarding a contract to Sundt Construction in the amount of $27,177,832.52 (GMP), and authorizing a change order allowance in the amount of $2,717.783 (10%), for a total authorized amount of $29,895,615.52. This project is funded by 2020 Street bonds and the Transportation Fund.
|