Title:
|
Fire Station 205 Rebuild - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 of 2 (District 2)
GMP No. 1 was awarded by Council in June 2025, and included temporary station site improvements, demolition of the existing fire station building and securing the long lead electrical equipment.
The project scope for GMP No. 2 is for the remainder of the project and includes the three apparatus bay fire station and site improvements.
Staff recommend awarding a construction services contract to the selected CMAR, FCI Constructors, Inc., in the amount of $9,407,484.72 (GMP No. 2), and authorizing a change order allowance in the amount of $940,748.47 (10%), for a total amount of $10,348,233.19. This project is funded by 2022 Public Safety bonds.
|