File #: 26-0751   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 8/31/2026
Title: Eastmark Aquatic Complex - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 6) The scope of this portion of the Eastmark Aquatic Complex Project is to review the project design for constructability, prepare and submit cost estimates, develop construction sequencing and an efficient construction schedule, create construction phasing plans, and develop the Guaranteed Maximum Price (GMP). Staff recommends selecting Sun Eagle Corporation as the CMAR for this project and awarding a pre-construction services contract in the amount of $136,295.00. This project is funded by 2024 Parks and Culture General Obligation (GO) Bond.
Attachments: 1. Council Report, 2. Council Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Eastmark Aquatic Complex - Pre-Construction Services and Construction Manager at Risk (CMAR) (District 6)

 

The scope of this portion of the Eastmark Aquatic Complex Project is to review the project design for constructability, prepare and submit cost estimates, develop construction sequencing and an efficient construction schedule, create construction phasing plans, and develop the Guaranteed Maximum Price (GMP).

 

Staff recommends selecting Sun Eagle Corporation as the CMAR for this project and awarding a pre-construction services contract in the amount of $136,295.00. This project is funded by 2024 Parks and Culture General Obligation (GO) Bond.