Ratification of the Emergency Purchase for Dobson Ranch Library Structural Column Repairs (District 3)
During the demolition phase of construction to the Dobson Library, the removal of landscape retaining walls and concrete walkways exposed structural damage to lower portions of two three-foot diameter concrete columns at the front entrance to the library. To avoid construction delays and mitigate the risk of further structural damage, an emergency purchase was issued on March 30, 2022 for the structural repairs that included the removal of corroded rebar and concrete, welding new rebar in place, and adding new concrete.
This emergency purchase resulted in a construction contract with Restruction, a division of Structural Preservation Systems, LLC, in the amount of $30,000, and an authorized change order allowance of $10,000, for a total contract amount of $40,000.
|