Title:
|
Northwest Water Reclamation Plant (NWWRP) - Food to Energy Program, Phase 1: Flare to Fuel Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 3)
This is the second, and final, GMP for this CMAR project. The scope of work for GMP No. 2 includes the installation, testing, and commissioning of previously purchased equipment, the procurement of the remaining materials not included in GMP No. 1, and the construction to connect the new system to the existing natural gas distribution system.
Staff recommends awarding the contract to the selected CMAR, Archer Western Construction, in the amount of $4,724,201.12 (GMP No. 2), and authorizing a change order allowance in the amount of $472,420.11 (10%), for a total amount of $5,196,621.23. This project is funded by the Capital Utility Fund-Solid Waste and the Environmental Compliance Fee Fund.
|
Title
Northwest Water Reclamation Plant (NWWRP) - Food to Energy Program, Phase 1: Flare to Fuel Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 3)
This is the second, and final, GMP for this CMAR project. The scope of work for GMP No. 2 includes the installation, testing, and commissioning of previously purchased equipment, the procurement of the remaining materials not included in GMP No. 1, and the construction to connect the new system to the existing natural gas distribution system.
Staff recommends awarding the contract to the selected CMAR, Archer Western Construction, in the amount of $4,724,201.12 (GMP No. 2), and authorizing a change order allowance in the amount of $472,420.11 (10%), for a total amount of $5,196,621.23. This project is funded by the Capital Utility Fund-Solid Waste and the Environmental Compliance Fee Fund.
|