Title:
|
Signal Butte Park Phase II Project, Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 2 (District 6)
GMP No. 1 includes the electrical scope and equipment, aiming to secure long-lead electrical items critical to the project's overall construction schedule. GMP No. 2 will be presented to Council at a future date for the remaining scope of work necessary to complete the project.
Staff recommend awarding a construction contract to Valley Rain Construction Corporation in the amount of $1,037,798.12 (GMP), and authorizing a change order allowance in the amount of $51,889.91 (5%), for a total authorized amount of $1,089,688.03. This project is funded by 2018 General Obligation Bonds through the Parks and Cultural Bond Program.
|