Central Mesa Reuse Pipeline - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 2)
GMP No. 2 includes the replacement of existing waterlines that are in conflict with the proposed alignment of the 36-inch Central Mesa Reuse Pipeline. The waterlines require relocation prior to the construction of the 36-inch reuse pipeline installation.
Staff recommends awarding a construction services contract to Garney Companies, in the amount of $12,719,521 (GMP No. 2), and authorizing a change order allowance in the amount of $635,976 (5%), for a total amount of $13,355,497. This project is funded by the Water Utility Systems Revenue Obligations.
|