File #: 21-1201   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 11/15/2021
Title: Greenfield Water Reclamation Plant (GWRP) Blower System Electrical Improvements - Pre-Construction Services and Construction Manager at Risk (CMAR) (Citywide) The City of Mesa, Town of Gilbert, and Town of Queen Creek (the “Owners”) seek to provide electrical improvements for redundancy in the Blower Building. The Blower Building provides air to the Aeration Basins which are essential to processing the plant influent. The electrical system providing power to the Blower Building needs to be replaced due to an aged startup system that is no longer supported and the lack of a redundant feed for the electrical system to properly operate in the case of an outage. Staff recommends selecting Ludvik Electric as the CMAR for this project, and awarding a pre-construction services contract in the amount of $82,680. This project is funded by the Greenfield Water Reclamation Plant Joint Venture Fund, with contributions coming from its members based on usage. Funding will be split amongst ...
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map, 3. Exhibit B - Aerial Project Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Greenfield Water Reclamation Plant (GWRP) Blower System Electrical Improvements - Pre-Construction Services and Construction Manager at Risk (CMAR) (Citywide)

 

The City of Mesa, Town of Gilbert, and Town of Queen Creek (the “Owners”) seek to provide electrical improvements for redundancy in the Blower Building.  The Blower Building provides air to the Aeration Basins which are essential to processing the plant influent.  The electrical system providing power to the Blower Building needs to be replaced due to an aged startup system that is no longer supported and the lack of a redundant feed for the electrical system to properly operate in the case of an outage.

 

Staff recommends selecting Ludvik Electric as the CMAR for this project, and awarding  a pre-construction services contract in the amount of $82,680.  This project is funded by the Greenfield Water Reclamation Plant Joint Venture Fund, with contributions coming from its members based on usage.  Funding will be split amongst the three partners, Mesa: $43,167.23 (52.21%); Gilbert: $29,351.40 (35.50%); and Queen Creek: $10,161.37 (12.29%).