Title
Downtown Utility Improvements, south of Main Street, Center to Robson (District 4)
City Project 10-458-001. This contract will increase the amount of this project by $15,000.00 to pay for changes due to differing site conditions that were discovered during the construction phase.
The original contract with The Fishel Company was $1,860,418.85 plus $186,041.89 (10%) for possible change orders, for an original contract award of $2,046,460.74. With this increase of $15,000.00, the new total project cost is $2,061,460.74. Funding is available from the existing (FY 11/12) Water Bond program.