Title:
|
Mesa City Hall Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) (District 4)
This GMP No. 1 is to minimize cost escalation and procurement delays. The scope includes mock-ups of concrete treatments and curtain wall sections; shop drawings for steel, elevator, curtain wall and terracotta materials; and procurement of steel, elevator and terracotta materials, as well as physical security appurtenances.
Staff recommends awarding a construction services contract to the CMAR, Okland Construction, in the amount of $1,400,000 (GMP), and authorizing a change order allowance in the amount of $98,000 (7%), for a total amount of $1,498,000. This project is funded by The Capital General Fund.
|