File #: 22-1565   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 12/8/2022
Title: Mesa City Hall Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) (District 4) This GMP No. 1 is to minimize cost escalation and procurement delays. The scope includes mock-ups of concrete treatments and curtain wall sections; shop drawings for steel, elevator, curtain wall and terracotta materials; and procurement of steel, elevator and terracotta materials, as well as physical security appurtenances. Staff recommends awarding a construction services contract to the CMAR, Okland Construction, in the amount of $1,400,000 (GMP), and authorizing a change order allowance in the amount of $98,000 (7%), for a total amount of $1,498,000. This project is funded by The Capital General Fund.
Attachments: 1. Presentation Slide, 2. Council Report, 3. Exhibit A
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Mesa City Hall Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) (District 4)

 

This GMP No. 1 is to minimize cost escalation and procurement delays. The scope includes mock-ups of concrete treatments and curtain wall sections; shop drawings for steel, elevator, curtain wall and terracotta materials; and procurement of steel, elevator and terracotta materials, as well as physical security appurtenances.

 

Staff recommends awarding a construction services contract to the CMAR, Okland Construction, in the amount of $1,400,000 (GMP), and authorizing a change order allowance in the amount of $98,000 (7%), for a total amount of $1,498,000.  This project is funded by The Capital General Fund.