Title:
|
Central Mesa Reuse Pipeline Plant, Construction Manager At Risk (CMAR), Guaranteed Maximum Price (GMP) No. 3 of 3 (District 1)
GMP No. 3 includes the construction of the proposed Intermediate Pump Station to facilitate delivery of reclaimed water to the Gila River Indian Community (GRIC) delivery point.
Staff recommend awarding a contract for this project to Garney Companies, in the amount of $15,040,620 (GMP No. 3), and authorizing a change order allowance in the amount of $752,031 (5%), for a total amount of $15,792,651. This project is funded by the Water Utility Systems Revenue Obligations.
|