Legislation Details
|
Type:
|
Contract
|
Status:
|
Agenda Ready
|
|
Title:
|
Monterey Park Expansion Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 6)
GMP No. 1 was awarded by Council in May 2022 and included site clearing and mass grading, installation of underground utilities, irrigation infrastructure, field lighting, fencing, landscaping, and some hardscapes.
The project scope for GMP No. 2 is for the remainder of the project and includes the park amenities: four LED lighted youth baseball/softball fields, lighted parking lot, irrigation system, new restroom/storage building, additional landscape and site improvements, four new regulation size pickleball courts, an age 2 to 5 playground, and a small library.
Staff recommends awarding a construction services contract to the selected CMAR, Hunter Contracting Co., in the amount of $5,456,823.80 (GMP No. 2), and authorizing a change order allowance in the amount of $272,841.19 (5%), for a total amount of $5,729,664.99. This project is funded by 2018 General...
|
Title
Monterey Park Expansion Project - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 2 (District 6)
GMP No. 1 was awarded by Council in May 2022 and included site clearing and mass grading, installation of underground utilities, irrigation infrastructure, field lighting, fencing, landscaping, and some hardscapes.
The project scope for GMP No. 2 is for the remainder of the project and includes the park amenities: four LED lighted youth baseball/softball fields, lighted parking lot, irrigation system, new restroom/storage building, additional landscape and site improvements, four new regulation size pickleball courts, an age 2 to 5 playground, and a small library.
Staff recommends awarding a construction services contract to the selected CMAR, Hunter Contracting Co., in the amount of $5,456,823.80 (GMP No. 2), and authorizing a change order allowance in the amount of $272,841.19 (5%), for a total amount of $5,729,664.99. This project is funded by 2018 General Obligation bonds and Capital General Funds.
|