Title
Gateway Boulevard and Aviation Way Utility and Roadway Improvements - Construction Manager at Risk (CMAR); Guaranteed Maximum Price (GMP) No. 2 (District 6)
In October 2021, Council approved GMP No. 1, an Intergovernmental Agreement (IGA) with Phoenix-Mesa Gateway Airport Authority (PMGAA), to construct City roadway and utility infrastructure to aid in the development of the east side of the Phoenix-Mesa Gateway Airport.
The project scope for this GMP No. 2 includes the procurement and construction of critical electrical materials and other associated tasks. Additional GMP’s for the remaining construction will be presented to City Council at a later date.
Staff recommends that awarding a construction services contract to the selected CMAR, Sundt Construction, Inc., in the amount of $614,681.04 (GMP No. 2), and authorizing a change order allowance in the amount of $61,468 (10%), for a total amount of $676,149.04. This project is funded by the 2020 Street Bonds, and the Transportation fund.