Title: Gateway Boulevard and Aviation Way Utility and Roadway Improvements - Construction Manager at Risk (CMAR); Guaranteed Maximum Price (GMP) No. 2 (District 6) In October 2021, Council approved GMP No. 1, an Intergovernmental Agreement (IGA) with Phoenix-Mesa Gateway Airport Authority (PMGAA), to construct City roadway and utility infrastructure to aid in the development of the east side of the Phoenix-Mesa Gateway Airport. The project scope for this GMP No. 2 includes the procurement and construction of critical electrical materials and other associated tasks. Additional GMP’s for the remaining construction will be presented to City Council at a later date. Staff recommends that awarding a construction services contract to the selected CMAR, Sundt Construction, Inc., in the amount of $614,681.04 (GMP No. 2), and authorizing a change order allowance in the amount of $61,468 (10%), for a total amount of $676,149.04. This project is funded by the 2020 Street Bonds, and the Transporta...
Attachments: 1. Council Report, 2. Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Gateway Boulevard and Aviation Way Utility and Roadway Improvements - Construction Manager at Risk (CMAR); Guaranteed Maximum Price (GMP) No. 2 (District 6)

 

In October 2021, Council approved GMP No. 1, an Intergovernmental Agreement (IGA) with Phoenix-Mesa Gateway Airport Authority (PMGAA),  to construct City roadway and utility infrastructure to aid in the development of the east side of the Phoenix-Mesa Gateway Airport.

 

The project scope for this GMP No. 2 includes the procurement and construction of critical electrical materials and other associated tasks.  Additional GMP’s for the remaining construction will be presented to City Council at a later date.

 

Staff recommends that awarding a construction services contract to the selected CMAR, Sundt Construction, Inc., in the amount of $614,681.04 (GMP No. 2), and authorizing a change order allowance in the amount of $61,468 (10%), for a total amount of $676,149.04.  This project is funded by the 2020 Street Bonds, and the Transportation fund.