File #: 24-0887   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 9/9/2024
Title: Southeast Water Reclamation Plant (SEWRP) Improvements, Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 1 (District 6) This project includes replacing existing Programmable Logic Controllers (PLC) and the Mixed Liquor Recycle (MLR) pumps. The existing PLCs and MLR pumps have reached the end of their service life and require replacement to continue the reliable operation of the plant. Staff recommend awarding a construction services contract for this project to McCarthy Building Companies in the amount of $3,765,229.70 (GMP), and authorizing a change order allowance in the amount of $376,522.97 (10%), for a total authorized amount of $4,141,752.67. This project is funded by Utility Systems Revenue Obligations.
Attachments: 1. Council Report, 2. Exhibit A - Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Southeast Water Reclamation Plant (SEWRP) Improvements, Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) No. 1 of 1 (District 6)

 

This project includes replacing existing Programmable Logic Controllers (PLC) and the Mixed Liquor Recycle (MLR) pumps. The existing PLCs and MLR pumps have reached the end of their service life and require replacement to continue the reliable operation of the plant.

 

Staff recommend awarding a construction services contract for this project to McCarthy Building Companies in the amount of $3,765,229.70 (GMP), and authorizing a change order allowance in the amount of $376,522.97 (10%), for a total authorized amount of $4,141,752.67. This project is funded by Utility Systems Revenue Obligations.