Northeast Public Safety Facility Project (NEPSF) - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) (District 5)
This GMP includes all scope necessary for the construction of the NEPSF including site preparation, building construction, mechanical and electrical systems, interior and exterior finishes, fire sprinkler system, security system, and all other associated work.
Staff recommends awarding a construction services contract to the CMAR, CORE Construction, Inc. in an amount of $32,330,843 (GMP), and authorizing a change order allowance of the amount in $1,616,542.15 (5%), for a total amount of $33,947,385.15. This project is funded by 2018 authorized Public Safety Bonds and Capital General funds.
|
Title
Northeast Public Safety Facility Project (NEPSF) - Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) (District 5)
This GMP includes all scope necessary for the construction of the NEPSF including site preparation, building construction, mechanical and electrical systems, interior and exterior finishes, fire sprinkler system, security system, and all other associated work.
Staff recommends awarding a construction services contract to the CMAR, CORE Construction, Inc. in an amount of $32,330,843 (GMP), and authorizing a change order allowance of the amount in $1,616,542.15 (5%), for a total amount of $33,947,385.15. This project is funded by 2018 authorized Public Safety Bonds and Capital General funds.
|