Pecos Road Basins And Storm Drain Improvements - Pre-Construction Services and Construction Manager At Risk (CMAR) (District 6)
This project consists of regional drainage improvements to approximately 3 miles of the Pecos Road corridor from Meridian Road to Ellsworth Road. The pre-construction phase work involves developing the project design, performing potholing, reviewing the design for constructability, preparing cost estimates, developing the project schedule, the project phasing plan and the Guaranteed Maximum Price (GMP). The GMP will be brought to Council for review and approval.
Staff recommends selecting Sundt Construction, Inc. as the CMAR for this project, and awarding a pre-construction services contract in the amount of $417,900, and authorizing a change order allowance in the amount of $41,790 (10%), for a total amount of $459,690. This project is funded by Local Street Sales Tax and the Transportation Fund.
|