Title:
|
Robson Electrical Substation East Bay Transformer - Switchgear Replacement CMAR Project - GMP No. 1 (District 2)
The scope of work for this project includes furnishing, installing, and constructing the conduits, foundations, structural steel, and switches necessary to support the replacement of the transformer and associated switchgear.
Staff recommends awarding the CMAR contract to ESS Corporation, based on the Guaranteed Maximum Price of $1,007,901, plus an additional $100,790 (10%) as a change order allowance, for the total award of $1,108,691. Project funding by 2014 authorized Electric bonds.
|