Title:
|
Central Arizona Project (CAP) Raw Water Pipeline, Guaranteed Maximum Price (GMP) No. 2 (District 6)
GMP No. 2 includes the purchase of materials and construction of the control structure at the CAP canal, the communication fiber-optic line from the Signal Butte Water Treatment Plant to the control structure, and construction of the north half of Elliot Road from Signal Butte Road to Mountain Road.
Staff recommends awarding the contract for the final phase of the project to Garney Construction, in the amount of $3,270,476.08, and authorize a change order allowance in the amount of $163,523.80 (5%). This allowance will only be utilized for approved change orders. Funding is available from 2014 authorized Water Bonds, Highway User Revenue Fund, and 2013 Street Bonds.
|