Northwest Water Reclamation Plant (NWWRP) - Odor Control Project (District 1)
The existing odor control complex consists of scrubber towers, large negative pressure fans, chemical storage and feed systems, and recirculation pumps. This infrastructure was originally constructed as part of the NWWRP expansion project completed in 2000 and has reached the end of its lifecycle and now requires replacement to maintain reliability.
Recommend award to the construction manager at risk, Hunter Contracting, for a total award amount of $1,402,162.67, based on the construction cost of $1,274,693.34, plus an additional $127,469.33 (10%) for contingencies. This project is funded by the 2010 authorized waste water bond fund.