Title
Gas SCADA (Supervisory Control and Data Acquisition) System Improvements (Districts 2, 3, 4 and 5)
The City's natural gas utility is required to monitor system pressures at the outlets of all regulator stations as part of the operations and federal code requirements. There is a cost savings to add the SCADA equipment as part of a larger project that installs the SCADA equipment at multiple locations, instead of individually as the regulator stations are constructed.
Recommend award to the lowest bidder, Hydro Controls, in the amount of $277,858.79, plus an additional $27,785.88 (10% allowance for change orders), for a total award of $305,644.67. This project is funded by 2010 authorized gas bonds.