File #: 20-0295   
Type: Contract Status: Agenda Ready
In control: City Council
On agenda: 3/16/2020
Title: Mesa City Center - Third Guaranteed Maximum Price (GMP No. 3) - ASU @ Mesa City Center (District 4) GMP No. 1 was approved by Council on November 4, 2019 and included infrastructure improvements to the City’s utilities, communications facilities, and streets needed to support the ASU building, the Plaza, the Studios and any future developments and improvements in the area. GMP No. 2 was approved by Council on December 9, 2019 and included general site demolition, excavation of the building site, building pad preparation, foundations, the concrete building structure, and associated items. This GMP is the third of the series of GMP’s relating to City Center work. The scope of work includes all remaining construction necessary to complete the ASU @ Mesa City Center building. Staff recommends awarding the contract for GMP No. 3 to the selected Construction Manager at Risk, DPR Construction, in the amount of $46,548,058, and authorizing a change order allowance in the amount of $2,327,...
Attachments: 1. Council Report, 2. Project Location Map
Date Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Mesa City Center - Third Guaranteed Maximum Price (GMP No. 3) - ASU @ Mesa City Center (District 4)

 

GMP No. 1 was approved by Council on November 4, 2019 and included infrastructure improvements to the City’s utilities, communications facilities, and streets needed to support the ASU building, the Plaza, the Studios and any future developments and improvements in the area.

 

GMP No. 2 was approved by Council on December 9, 2019 and included general site demolition, excavation of the building site, building pad preparation, foundations, the concrete building structure, and associated items.

 

This GMP is the third of the series of GMP’s relating to City Center work. The scope of work includes all remaining construction necessary to complete the ASU @ Mesa City Center building.

 

Staff recommends awarding the contract for GMP No. 3 to the selected Construction Manager at Risk, DPR Construction, in the amount of $46,548,058, and authorizing a change order allowance in the amount of $2,327,402.90 (5%), for a total amount of $48,875,460.90.  This project is funded by the Economic Investment Fund and Excise Tax Bonds, with an additional $10 million from ASU sources.