Title:
|
Desert Well No. 20 Equipping Project (District 6)
Desert Well No. 20 will pump water to the existing 8-million-gallon reservoir at the Signal Butte Water Treatment Plant via a well collection waterline in Signal Butte Road. New development in Southeast Mesa has increased water demand and Desert Well No. 20 is now required to meet this demand.
Staff recommends awarding the contract to the lowest, responsible bidder, Currier Construction Inc., in the amount of $1,234,317, and authorize a change order allowance in the amount of $123,432 (10%), for a total award of $1,357,749. Funding is available in the 2014 authorized Water System Revenue Bond.
|